For a company-wide system you assign the schedule to the intrusion zone in both the Supervisor and the remote host controller.
Prerequisites: You are working in the Supervisor station, followed by working in the remote controller station. The intrusion
zone already exists.
- To begin in the Supervisor station, click .
- To select the intrusion zone, double-click a zone and click the Intrusion Zone tab.
- Click the chevron next to the
Zone Schedule property, select the schedule you created from the Ref Chooser, and click OK.The name of the schedule appears in the Zone Schedule property.
When the schedule transitions to true, the system arms the zone and performs any associated actions.